The court’s findings

Contract 22102021 of 22 October 2021 covered manufacture, foundations and assembly of a MODODOMUS S172 house. The customer paid 90 000 EUR (2 660 000 UAH) in advance. Delivery was due on 20 May 2022. The court found non-performance; the first-stage delay began on 21 January 2022, before the full-scale invasion. The advance remained unpaid at the time of the hearing. The defendant’s force-majeure and late-payment arguments did not relieve him of liability.

Read case 760/9353/22 →